Children’s Hospital Addition

In August 2008, Harris began a 275,000-square foot addition to the existing Minneapolis Children’s Hospital consisting of an eight-story vertical expansion, a new central plant and front entry along with extensive renovations.

Harris provided complete design-build engineering and installation of all mechanical, plumbing, medical gases and temperature control systems for this project. Manufacturing ductwork and piping was key to streamline the installation and meet an aggressive “fast-track” schedule.

The eight-story addition included an energy plant with new chillers and boilers to serve the new and future additions including new patient rooms, laboratory, emergency department and nine operating rooms.

A new four-story addition was added to the Chicago Avenue side of the building. Levels 1 and 2 included a main entrance with performance areas, café, welcome desk area and a skyway connection to the existing medical office building. The upper levels included ICC support, NICU and CVICU patient rooms.

Read more about Our expertise in:

See more projects
275,000
square feet (eight-story + four-story additions)
  • Location
    Minneapolis, MN
  • Owner
    Children's Hospitals and Clinics of Minnesota
  • General Contractor
    Knutson Construction
  • Architect
    AECOM
  • Engineering Consultant
    Harris
  • Market
    Healthcare
  • Expertise
    Construction
  • Delivery Method
    Design-Build
  • Scope
    BIM, Cost Estimating, Engineering and Design, Fire Alarm System Installation, HVAC, Insulation, Manufacturing, Medical Gas Piping, Plumbing, Preconstruction Services, Process Piping, Temperature Controls, Test and Balance
  • Completion Date
    2015